From the Montpelier Board of Works & Safety meeting on July 15, 2026

Cooley's has the variable frequency drive for the main lift station, but Water Superintendent Chase Perry has been unable to reach them to schedule installation — the contact may be on vacation. The approved cost is $6,455. Perry noted the VFD has "been out" for an extended period and plans to try reaching Cooley's again later this week.

A variable frequency drive controls the speed of the lift station pump motor, improving efficiency and reducing wear.